4.0 Procurement and Project Schedule
The Village currently anticipates conducting procurement and execution of the Project within this timeframe and according to these milestones:
The Village reserves the right to revise the milestones and timeframes identified above at their sole discretion. Because of Project funding constraints, construction activities (defined as clearing and grubbing or breaking ground, but not necessarily mobilization or temporary facility installation) cannot be started prior to July 1, 2016. Proposers are encouraged to include alternatives that detail early-finish scenarios regarding the substantial completion and project closeout end dates indicated hereinabove, and an expedited development of their Guaranteed Maximum Price (GMP) Amendment.
5.0. RFP Information and Reference Materials
This RFP document is accompanied by the following references and forms that are provided to allow Proposers to fully develop and detail their Proposals. Those reference materials and forms include: